Check total float and the critical path in an .xer file

When a schedule update arrives as an .xer file, the first questions are usually the same: what is critical, how much float is left, and is anything showing negative float? You can answer all three without a P6 license.

Open your .xer file Free Gantt chart and activity table. Nothing is uploaded.

See the float in a minute

  1. Drop the .xer file into the XER Viewer. It is read in your browser and never uploaded. Viewing is free.
  2. If the file holds several projects, pick the one you want.
  3. Read the line above the chart: it names the project calendar, its hours per day, and how many activities have total float of zero or less.
  4. On the Gantt chart tab, leave Critical (total float ≤ 0) ticked. Those activities are drawn in red; untick it to see every bar in one color.
  5. Switch to the Activity table tab to see the Total Float column next to the early and late dates of every activity.

What the numbers mean

The values are exactly what the file holds, as of its data date. The viewer doesn't recalculate the schedule, so if the logic was changed after the last schedule run in P6, the float won't reflect it until the scheduler runs it again and re-exports.

Trace the critical chain

The Predecessors column lists each link with its type and lag, such as "A1020 FS" or "A2010 SS +3". Start at the finish milestone, look up its red predecessor, and keep going back. The search box jumps to any activity by ID or name, which makes this quick even on a large schedule.

Things worth a question when you trace it: a red chain that breaks off partway (an open end or a constraint holding the dates), long lags standing in for real work, and activities with very large float that should be driving something.

Critical by float, not by longest path

The viewer marks an activity critical when its total float is zero or less. That is P6's default definition. If the project is set to define critical activities by longest path, P6 can show a slightly different set. The float values themselves don't change.

Sort and filter in Excel

The Excel export ($19 once, or $7 for 24 hours) has a Total Float column in days, a Critical column (Yes or No) and the predecessors for every activity, with filters already on, so you can sort by float or filter to just the critical work. A Relationships sheet lists every link with its type and lag. Before paying, you can download the first 20 activities free to check the layout.

What this won't do

It shows total float, not free float, and it doesn't run a time impact analysis or a what-if. For those, someone needs P6.

Open your .xer file Free Gantt chart and activity table. Nothing is uploaded.

Primavera P6 is a trademark of Oracle; Excel is a trademark of Microsoft. We are not affiliated with Oracle or Microsoft.