Open a construction schedule sent as an .mpp file

General contractors and owners' reps build schedules in Microsoft Project and send the .mpp file to every trade. If you're a subcontractor or supplier without Project, here is how to read it, find your scope and keep up with updates.

Open your .mpp file Free Gantt chart and task table. No sign-up.

Open the schedule

Drop the .mpp file into the MPP Viewer. You get the Gantt chart and the full task table: WBS numbers, durations, start and finish dates, percent complete, predecessors and who is assigned. It works on the office PC, a Mac or a Chromebook, with nothing to install. Viewing is free.

Find your tasks and dates

Put it in Excel for your own planning

The Excel export ($9 once, or $7 for a day) gives you one row per task with the outline kept, real dates you can sort and filter, percent complete and resources. Filter it to your trade and you have a look-ahead list for crew and material planning.

Want to check the export before paying? Open your schedule and click Excel: there is a free sample of the first 20 tasks.

When the GC sends an update

Open the new file the same way. Compare the start and finish dates of your tasks with the last version, and look at the predecessors: a slipped upstream task is the usual reason your dates move. If you get a new schedule every week or two, install the viewer so the file opens with a double-click from the email.

What you can't do without Project

You can read, filter and export the schedule, but not edit it and send back an .mpp file. Schedule changes go through the GC's scheduler, usually as a marked-up PDF or a list of dates from your Excel export.

Open your .mpp file Free Gantt chart and task table. No sign-up.

Microsoft Project is a trademark of Microsoft. We are not affiliated with Microsoft.