Compare two versions of a Microsoft Project file

You have last month's plan and this month's update, and you need to know what changed: did the finish date move, which tasks slipped, what was added or taken out. Here are three ways to see it, with and without Microsoft Project.

Open your .mpp file Free Gantt chart and task table. No sign-up.

With Microsoft Project: Compare Projects

Project desktop has this built in. On the Report tab, choose Compare Projects, pick the other version, and choose which task and resource tables to compare. Project makes a comparison report that lists only the differences between the two versions, with a legend for its color coding, and you can save it. It compares tasks and resources, not assignments. Microsoft lists it for Project Standard and Professional 2016, 2019 and 2021, Project Standard 2024 and the Project Online desktop client: Compare two versions of a project.

So you need Project installed on Windows. If you're the owner, the client or a subcontractor who receives the plan, you often don't have it.

Without Project: the MPP Viewer

  1. Open the first version in the MPP Viewer.
  2. Click Compare with another version and pick the other file. The plan you opened first is treated as the older one; Swap turns that round.
  3. The Compare tab shows the summary.

Free, you see:

A task counts as changed when its name, start, finish, duration, percent complete, predecessors or place in the WBS differ. Tasks are matched by the unique ID Project gives each task, so a task that was renamed or moved is still the same task. If the two files don't share IDs (a plan rebuilt from scratch, for example), tasks are matched by WBS and name instead.

The full change list, and a change report in Excel (Changed, Added and Removed sheets, old and new values side by side) and CSV, come with the $9 license, which also unlocks the Excel, CSV and PDF exports for every plan you open. It works the same on Windows, Mac and Chromebook. The files are read on our server and deleted as soon as they have been read.

The same works for Primavera P6 schedules: see how to compare two P6 schedule updates.

By hand in Excel

  1. Export each version to Excel, from Project or from the MPP Viewer.
  2. Put the two task lists on separate sheets of one workbook.
  3. On the new sheet, add a column that looks up the old finish date with XLOOKUP on the WBS code (or on the task name, if the plan has no WBS codes), and a column for the difference between the new and old finish.
  4. Filter that column for anything that isn't zero. Tasks the lookup can't find are new; to find removed tasks, do the same lookup the other way round.

It works, but it takes a while on a big plan, and a renamed task or a changed WBS code shows up as one removed and one added task.

What to look at first

Open your .mpp file Free Gantt chart and task table. No sign-up.

Microsoft Project is a trademark of Microsoft. We are not affiliated with Microsoft.