Move a Microsoft Project plan into Asana or monday.com

Asana and monday.com both import spreadsheets, and we couldn't find either one documenting a way to read an .mpp file. If your team is moving off Microsoft Project and the plans are .mpp files nobody can open any more, here's how to get them in, including the date formats each importer is fussy about.

Open your .mpp file See the plan free, then export it for the import.

Step 1: get the plan out of the .mpp

  1. Open the MPP Viewer and drop the .mpp, .mpx or Project .xml file on the page. The Gantt chart and full task table appear free, so you can check it's the right version of the plan.
  2. Click Excel. On a plan with more than 20 tasks, you can download a free sample with the first 20 tasks and do a test import with it first. The full export is $9 once for every project you open, or $7 for 24 hours if you're moving a batch of plans in one sitting.

The Excel file's first tab, Tasks, has ID, WBS, Task Name, Duration, Start, Finish, % Complete, Predecessors, Resource Names, Milestone, Critical, Baseline Start, Baseline Finish and Notes. Start and Finish are real dates. The second and third tabs list the resources (with their email addresses, when the plan has them) and who is assigned to which task.

We use the Excel export here rather than the CSV, because the CSV writes dates the way Project shows them (Mon 3/2/26), and neither importer below asks for that format.

Into Asana

Asana's CSV importer takes a CSV file, so an Excel file needs saving as CSV first, and dates have to be in the US month/day/year format (Asana: introducing the CSV importer). The same article says assignees are matched by work email address, and that start dates and custom fields need a paid plan; on a free plan those columns go into the task description.

  1. Open the Excel export. On the Tasks tab, select the Start and Finish columns and set their number format to a date like m/d/yyyy.
  2. Delete the summary rows (shown in bold) if you only want the real work as tasks, and delete columns you don't want to bring across.
  3. If you want tasks assigned, replace the names in Resource Names with each person's work email. The Resources tab has the emails stored in the plan, if any.
  4. Save the Tasks tab as CSV (Excel saves only the open tab), then run Asana's CSV import and map Task Name to the task name, Finish to the due date, and Start to the start date.

Asana's help center has a full page on preparing data for the CSV importer, including sections and subtasks: Prepare data for CSV import into Asana.

Into monday.com

monday.com imports .xlsx, .xls and .csv files up to 10 MB, and only the first tab of an Excel file, which is where the Tasks sheet is (monday.com: Import files from Excel). Its help page also says imported dates must be in ISO format, such as 2021-10-23.

  1. Open the Excel export. Select the Start and Finish columns and set a custom number format of yyyy-mm-dd, then save.
  2. In monday.com, choose Import Data, then Excel, and upload the file. Pick the header row, then pick Task Name as the column that becomes the item names.
  3. Set Start and Finish to Date columns. On a new board, monday.com imports columns as Number, Status, Email, Date or Text; importing into an existing board can also map to Timeline and People columns, per the same help page.

Per monday.com's page, subitems in a spreadsheet arrive as ordinary items that you can convert to subitems afterwards, and a new board takes up to 8,000 rows. The WBS column (1, 1.1, 1.2.3) tells you which tasks belong under which.

What doesn't come across by itself

Only need to read the plans?

If some old plans just need to be looked at now and then, don't migrate them. Viewing is free in the browser viewer on any computer, and a PDF Gantt chart is an easy archive copy.