Compare two P6 schedule updates without P6

The contractor sent this month's schedule update as an .xer file, and you need to know what changed since last month: did the finish move, where did the float go, what just became critical, and did anyone change the logic. Here's how to check, with or without P6.

Open your .xer file Free Gantt chart and activity table. Nothing is uploaded.

What owners check between updates

In P6: Claim Digger

P6 has a comparison tool called Claim Digger (also named Schedule Comparison), which compares two projects, or a project and one of its baselines. Oracle lists it for P6 Professional and the P6 EPPM client: P6 EPPM to Primavera Cloud Migration Guide. It runs inside P6, so both updates have to be imported into a P6 database first. If you're the owner or the architect, you usually don't have a P6 license.

Without P6: the XER Viewer

  1. Open last month's .xer in the XER Viewer.
  2. Click Compare with another update and pick this month's .xer. The file you open first is treated as the older one; Swap turns that round.
  3. The Compare tab shows the summary.

Free, you see:

An activity counts as changed when its Activity ID, name, dates, original or remaining duration, percent complete, total float, predecessors (including type and lag) or WBS differ. Activities are matched by Activity ID, then by P6's internal activity number, so a renamed or renumbered activity is still the same activity. Both files are read in your browser and never uploaded.

The full change list, and a change report in Excel (Changed, Added and Removed sheets, with old and new dates, durations and total float, and the change in days) and CSV, come with the $19 license, which also unlocks the Excel, CSV and PDF exports for every schedule you open.

Durations and float are in days of each activity's calendar, as the file holds them. "Critical" here means total float of zero or less, P6's default; if the project uses longest path, P6 can mark a slightly different set.

By hand in Excel

  1. Export both updates to Excel, from P6 or from the XER Viewer (its Activities sheet has Activity ID, dates, total float and predecessors).
  2. On this month's sheet, add columns that look up last month's finish and total float with XLOOKUP on Activity ID.
  3. Add a column for the float change and filter for activities whose float dropped, or whose float is now zero or less while last month's wasn't.
  4. For logic, compare the Relationships sheets the same way, keyed on predecessor and successor ID.

Fine for a small schedule; on a few thousand activities, the viewer's comparison is quicker.

Comparing Microsoft Project plans instead? See how to compare two versions of a Microsoft Project file.