Open the submittal
- Save the .xer file from the email or the submittal system.
- Drop it into the XER Viewer. If the file holds several projects, pick the one you're reviewing.
The summary line shows the data date, the number of activities and how many are critical. The file is read inside your browser and never uploaded, which matters when the schedule is confidential. Viewing is free.
What to look at first
- Data date. It should match the update period. The dashed line on the Gantt chart marks it, so anything left of the line that isn't finished is behind.
- Critical path. Activities with total float of zero or less are red. Check that the red chain makes sense for the job and ends at the contract completion milestone.
- Negative float. The activity table shows total float in days. Negative numbers mean the schedule shows the job finishing late.
- Logic. The predecessor column lists each link with its type and lag, such as A1020 SS +2. Long lags and lots of start-to-start links are worth a question.
- Progress. Percent complete and actual dates show what the contractor says happened this period.
Use the search box to jump to an activity by ID or name when you're checking a specific claim.
What changed since last month
With this month's update open, click Compare with another update and pick last month's .xer. You see free how far the project finish moved, how many activities became critical (total float now zero or less), how many activities changed, were added or were removed, and the first 10 changes with old and new dates, remaining duration, total float and progress side by side. The full list, and a change report in Excel and CSV, come with the license. Both files are read in your browser and never uploaded.
A schedule health check
The Schedule check tab runs a check based on the DCMA 14-Point Assessment: open ends, leads and lags, hard constraints, high and negative float, long durations and dates on the wrong side of the data date, each against the usual threshold. The results are free; see how to run a DCMA 14-point check without P6.
Deeper checks in Excel
The Excel export ($19 once, or $7 for 24 hours) puts every activity on one sheet with early and late dates, total float, percent complete, a critical flag and its predecessors, plus a Relationships sheet with every link. In Excel you can filter for blank predecessors to find open starts, sort by total float, or compare this month's export with last month's side by side. The PDF prints the Gantt chart for the meeting. You can download the first 20 activities free to check the layout.
What this won't do
This is a viewer. It shows the schedule exactly as the contractor exported it. It doesn't reschedule or run a time impact analysis; for that, someone needs P6.