Run a DCMA 14-point check on a P6 schedule without P6

The DCMA 14-Point Assessment is the most common health check for a CPM schedule: owners, schedulers and claims consultants run it on the baseline and on every update. If the schedule came to you as an .xer file and you don't have P6, here's how to run it anyway, and how to read the results.

Open your .xer file Free Gantt chart and activity table. Nothing is uploaded.

Run it in the browser

  1. Open the .xer in the XER Viewer. It is read in your browser and never uploaded.
  2. Click the Schedule check tab.

You see all 14 checks with the result (pass, fail, n.a. or not run), the number behind it and the threshold, plus a score such as "7 of 8 checks passed". That part is free. The list of activities behind each result, and a check report in Excel (a summary sheet plus one sheet per failed check) and CSV, come with the $19 license, which also unlocks the Excel, CSV and PDF exports. The check is based on the DCMA 14-Point Assessment; it isn't endorsed by DCMA.

The 14 checks and their thresholds

  1. Logic. Incomplete activities with no predecessor or no successor: 5% or less.
  2. Leads. Relationships with a negative lag: none.
  3. Lags. Relationships with a positive lag: 5% or less.
  4. Relationship types. Finish-to-start links: 90% or more.
  5. Hard constraints. Activities with a constraint that fixes a date (Start On, Finish On, Start On or Before, Finish On or Before, Mandatory Start, Mandatory Finish): 5% or less.
  6. High float. Total float over 44 working days: 5% or less.
  7. Negative float. Total float below zero: none.
  8. High duration. Original duration over 44 working days: 5% or less.
  9. Invalid dates. Actual dates after the data date, or forecast dates before it: none.
  10. Resources. Activities with no resource assigned. Reported, not scored, since many schedules aren't resource loaded.
  11. Missed tasks. Activities whose baseline finish is on or before the data date that finished late or haven't finished: 5% or less.
  12. Critical path test. Add a big delay to a critical activity and check that the project finish moves by the same amount.
  13. CPLI (critical path length index): (critical path length + project total float) / critical path length, 0.95 or more.
  14. BEI (baseline execution index): activities finished / activities due by the data date, 0.95 or more.

The counts leave out milestones, level of effort activities, WBS summaries and completed activities, except where a check is about completed work (invalid dates, missed tasks, BEI). The relationship checks count the links into incomplete activities. Durations and float are in working days of each activity's calendar.

What "n.a." and "not run" mean

Reading the results

A fail is a question to ask, not a verdict. Open ends often sit at the start and the finish milestones; a handful of lags may be real cure or lead times; high float can be work that genuinely has room. What matters is the pattern from one update to the next: negative float growing, logic disappearing, hard constraints appearing to hold dates in place. To see what moved between two updates, use the update comparison, and for the rest of a review see how to review a contractor's .xer schedule.

Microsoft Project plans get the same check in the MPP Viewer; there the date-based checks need a status date in the plan.