In your browser
- Open the MPP Viewer.
- Drop your .mpp, .mpx or Project .xml file on the page. The Gantt chart and the task table appear free, so you can check it's the right plan before you export anything.
- Click CSV. The first time it asks for a license: $9 once, then CSV, Excel and PDF exports work in that browser for every project you open. Only need one batch today? The 24-hour pass is $7.
The columns
One row per task, in the same order as the plan, with a header row:
ID, WBS, Task Name, Duration, Start, Finish, % Complete, Predecessors, Resource Names, Milestone, Summary, Notes
- Dates are written the way Project shows them, such as Mon 3/2/26.
- Predecessors use the task IDs and link types Project shows, such as 4FS+2 days or 7SS.
- Milestone and Summary are Yes or No, so you can drop the summary rows in the importer and keep only the real work.
- Resource Names is the comma-separated list of who is assigned, in one cell.
The file is UTF-8 with a byte order mark, so accented names and other languages open correctly when you double-click it into Excel.
Importing it somewhere else
In the target tool's import screen, map Task Name to the title, Start and Finish to the date fields, and % Complete to progress. Two things to check after the import:
- The outline is in the WBS column (1, 1.1, 1.2.3), not in the task name. If the tool supports parent tasks, use WBS to rebuild the hierarchy; if not, filter out the Summary rows.
- Predecessors come across as text. Most tools don't rebuild links from a CSV, so check the important dependencies by hand.
CSV or Excel?
CSV holds the task table only. If you also need the resource list and who works on which task with units and work, use the Excel export: it has Tasks, Resources and Assignments sheets, real Excel dates and the baseline dates. Same license covers both. For a shared sheet, see MPP to Google Sheets.
With Microsoft Project
If someone near you has Project, File, Save As, CSV runs the export wizard where you pick the fields yourself. The CSV is a copy: changes made to it don't flow back into the .mpp.