The resource list
- Drop the .xer on the XER Viewer. It is read in your browser and never uploaded.
- Click the Resources tab.
You get every resource assigned to an activity in the project, with its ID, name, type (labor, nonlabor or material), the number of activities it is on, and its total budgeted units. If the tab says no resources are assigned, the schedule isn't resource loaded, or it was exported without them.
Which activities a resource is on
On the Activity table tab, the last column lists each activity's resources. Type a resource name into the search box ("Find activity ID or name") on the Activity table or Gantt chart tab: the list narrows to the activities that resource is assigned to, with their dates and float. That is the quickest way to see, say, everything the electrical crew has coming up.
Units by activity, in Excel
The Excel export has two sheets for this:
- Resources: the same list as the tab, with budgeted units.
- Assignments: one row for each resource on each activity, with the activity ID and name, the resource, and the budgeted, actual and remaining units.
With a pivot table on the Assignments sheet you can total remaining units by resource, or look up each activity's dates on the Activities sheet by activity ID. Units are the numbers stored in the file, as P6 wrote them.
Exports are $19 once for every schedule you open, or $7 for 24 hours. The first 20 activities are free to download in Excel to check it on your file.
What isn't shown
- Costs and resource rates.
- Resource curves and the period-by-period spread of units (the resource histogram).
- Resources that exist in the file but aren't assigned to any activity in the project.